Decision - Valley Gardens Phase 3 (Royal Pavilion to Seafront) Results of public consultation and approval of Final Preliminary Design

skip navigation and tools

Decision details

Valley Gardens Phase 3 (Royal Pavilion to Seafront) Results of public consultation and approval of Final Preliminary Design

Decision Maker: Environment, Transport & Sustainability Committee, Council

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Valley Gardens Phase 3 - preliminary design of highway and public realm remodelling from Edward Street Junction - Royal Pavilion - Old Steine to the Seafront including the A23/A259 Junction ('Aquarium Roundabout').

Approve continued investment.

Approve preferred option to progress to detailed design.

Decision:

1)           That the Committee notes the results of the public consultation and stakeholder engagement on the preferred design option for the Valley Gardens Phase 3 project, as set out in Appendix 1 and Appendix 2 of this report.

 

2)           That the Committee approves the Final Preliminary Design for the Valley Gardens Phase 3 project, as attached in Appendix 3 of this report, and agrees that it should be progressed to the detailed design stage which will include further public consultation and stakeholder engagement.

 

3)           That the Committee agrees that officers progress design work for the proposed improvements to the A259/Duke’s Mound/Madeira Drive junctions, in liaison with the council’s Waterfront project team.

 

4)           That the Committee authorises officers to procure professional services/contract(s) for the detailed design and construction stages of the Valley Gardens Phase 3 project, and notes that this authorisation will enable officers to procure and award either a design and build contract or separate contracts for the design stage and the construction stage, and notes that an update on these procurements will be provided to a future committee meeting.

 

5)           That the Committee approves the revised design of the Marlborough Place - Edward Street junction, as shown in Appendix 3 of this report, which will   supersede the design of the southernmost section of the Valley Gardens Phases 1&2 project agreed by this Committee in December 2017, and agrees that the design can be progressed to the detailed design stage and delivered as part of the current construction programme for Valley Gardens Phases 1&2.

 

6)           That the above recommendations are agreed subject to obtaining independent legal advice to the satisfaction of officers, after consultation with the Chair and Opposition Spokespersons.

Report author: Oliver Spratley

Publication date: 08/02/2019

Date of decision: 07/02/2019

Decided at meeting: 07/02/2019 - Environment, Transport & Sustainability Committee