Decision - Portslade Sports Centre - Replacement 3G Pitch Project
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Portslade Sports Centre - Replacement 3G Pitch Project
Decision Maker: Policy, Resources & Growth Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Seeking committee approval for the project to
replace of the current astro turf pitch with a new 3G All Weather
Pitch
Decision:
RESOLVED: That the Committee –
(i) Approved the submission of a bid by the council to the Football Foundation for at least £0.250m funding for the delivery of the replacement 3G pitch project at Portslade Sport Centre, and subject to the award of that funding;
(ii) Approved the delivery of the replacement 3G pitch project at Portslade Sport Centre;
(iii) Approved a capital budget for this project of £203,000 based on the overview in paragraph 3.10 including the allocation of identified Section 106 funds and direct revenue funding from existing budgets;
(iv) Granted delegated authority to the Executive Director for Economy, Environment & Culture to enter into any contracts necessary to deliver the replacement 3G pitch
project.
(v) Approved the establishment of a reserve of £25,000 per annum to support the long term sustainability and future replacement costs of major components of the 3G pitch.
Report author: Kerry Taylor
Publication date: 11/10/2018
Date of decision: 11/10/2018
Decided at meeting: 11/10/2018 - Policy, Resources & Growth Committee