Decision - Prince Regent Swimming Complex - Mechanical and Electrical Replacement Works
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Prince Regent Swimming Complex - Mechanical and Electrical Replacement Works
Decision Maker: Policy, Resources & Growth Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To replace heating, ventilation and air
conditioning systems at the Prince Regent Swimming
Complex.
Decision:
RESOLVED – That the Committee:
1) Approve the procurement of a contract for works to replace the air-handling system and associated works as listed in 3.10 at the Prince Regent Swimming Complex.
2) Grants delegated authority to the Executive Director for Economy, Environment & Culture (Acting or otherwise), in consultation with the Executive Director, Finance & Resources to carry out the procurement and award of the contract referred to in 2.1 above.
3) Approve a capital budget of £0.728m for this project which will be funded as detailed in paragraph 3.11.
Report author: Ian Shurrock
Publication date: 15/07/2016
Date of decision: 14/07/2016
Decided at meeting: 14/07/2016 - Policy, Resources & Growth Committee